Orange County and the City of Winter Garden are in the process of designing a master stormwater system for Historic East Winter Garden Neighborhood. A conceptual design and identifying preliminary costs for the project are currently in the works by the City. A map of the historic area is shown below
East Bay, Christopher, Saba, and Trumbo Street Stormwater Project
The project area consists of four residential streets (East Bay Street, Christopher Street, Trumbo Street, and Saba Avenue). The proposed construction improvements will comprise of new five-foot sidewalks on both sides of the roadways, roadway milling and resurfacing, a closed drainage system, and two retention ponds. This project also includes the construction of a water main for the City of Winter Garden throughout the project area.


Construction Timeline:
The current project schedule anticipates advertising the project for bids in April-May 2024 so that construction can start in fall of 2024. Construction will take approximately one year to complete.
Project Typical Section: