Capital Improvements
View Department Contact informationCapital Improvement Projects
City of Winter Garden
300 West Plant Street
Winter Garden, FL 34787
Phone: 407.656.4111
Staff
Robin Hayes, Finance Director
rhayes@wintergarden-fl.gov
Phone: 407.656.4111 ext. 2313
Don Cochran, Assistant City Manager for Public Services
dcochran@wintergarden-fl.gov
Phone: 407.656.4111 ext. 2263
Marc Black, Capital Improvements Project Administrator
mblack@wintergarden-fl.gov
Phone: 407.656.4111 ext. 2317
In November 2008, the City adopted the annual update to the Capital Improvement Element (CIE) that meets the new state planning requirements passed in 2005 and 2006. The list of improvements matches the list of projects in the City's five year capital improvement plan of the City budget and compares to our projected growth and adopted level-of-service for the required services and facilities.
Both amendments have been approved by the State planning agency and are in effect. The City of Winter Garden was one of only 40 cities in Florida that were considered in compliance by the December 2008 deadline for the CIE update.
| Capital Improvement Projects Report | ||||
|---|---|---|---|---|
| Project Name | Location | Scope | Estimated Start Date | Completion Date |
| Trunk Line "C" Reuse Water & Force Main | Serve Neighborhoods South of SR 50 | Extend wastewater force mains & reuse water mains. |
Bid Phase | |
| CR 545 Segment 1 Road Improvement | Tilden Road intersection | Traffic signal improvements. Widen road to 4 lanes: 1,400' west of intersection & 1,100' south of Stoneybrook West Boulevard. Project funded by developer. | Under Design | |
| CR 545 Segment 2 Road Improvement | Tilden Road Intersection to Hickory Hammock | Widen road to 4 lanes from 1,100' south of Stoneybrook West Parkway to 2,000' north of Stoneybrook Parkway. Project funded by developer. | Under Design | |
| Marsh Road / CR 545 | Western Line of Hickory Hammock Pond | Widen road to four lanes from CR 545 to 2,700' west of Marsh Road. Project funded by developer. | Under Design | |
| East Plant Street / West Crown Point Improvements | Plant Street & West Crown Point Road Intersection | Widen road to 4 lanes. Add left turn lanes. Install traffic signals. |
Complete | |
| SR 50/Colonial Improvement Project | SR 429 to Avalon Road | Widen road to 6 lanes. Utility relocation. New traffic signals. New street lights. New medians. Landscape enhancements. |
Dec-09 | Dec-11 |
East Plant St Segment III |
West Crown Point Road to SR 429 |
Widen road to 4 lanes Install traffic signal |
Bid Sept-10 |
May-11 |
| Park Ave. Resurfacing | Park Ave. from Plant St to Tilden |
Resurfacing | Complete | |
| Boyd St. Resurfacing | Boyd St. from Tilden to Division |
Resurfacing | Complete | |
| 9th St. Sewer Replacement | 9th St. from SR50 to East Cypress St. |
Replacement of 30-inch sewer main | July-10 | Sept-10 |
| Dillard Street | Dillard St. between Plant and Tilden |
Road reconstruction with water and sewer rehabilitation | Under Design | |
| Main Street | Main St. between Plant and Tilden |
Road reconstruction with water and sewer rehabilitation | Under Design | |
| Coluso Drive Drainage | Off of Markel Drive | Installation of drainage improvements | April-10 | Complete |
| Roper Drive Drainage | Roper Drive between Lakeview and Tilden |
Installation of drainage improvements | Aug-10 | Sept-10 |
| South Main Improvements | South Main St. from Smtih to Tremaine |
Road reconstruction with water and sewer rehabilitation | Under Design | |
| Roper Road East | Roper Road between Daniels Road and Reaves Road | Road improvements with water and reuse water main installation |
Bid Phase | |