Stoneybrook West Parkway / Roberson Road / Windermere Road Roundabout Improvements

Image of approved Stoneybrook Roberson Windermere Roundabout overlaid on top of satellite view.

The City has worked with Orange County and the City of Ocoee to revise the intersection from signalized traffic control to a roundabout.  The project consists of relocating utilities such as water, sewer, power and communications as well as new stormwater collection piping and inlets.  The project’s scheduled normal working hours will be 7:00 am to 5:00 pm, Monday through Friday, although some operations (i.e. paving etc.) may need to occur at night when there is less traffic.

The project started in July 2018 and was substantially completed in April of 2019. Currently, crews are finishing the project's landscaping.